NEC vs JCT: Compensation Events v Variations, Extensions of Time and Loss and Expense
By Sheldon Wright MCICES. Last reviewed November 2026. Compares the JCT Standard Building Contract 2016 with the NEC4 Engineering and Construction Contract, with NEC3 differences noted.
Most comparisons of JCT and NEC start with the philosophy: JCT is the traditional building contract, NEC is the collaborative one written in plain English. That is true, and it is not where the money goes. The money goes in how each contract deals with change: who decides, on what basis, how quickly, and what happens if somebody misses a date.
I have spent most of my career on NEC and a good part of it alongside people who learned their trade on JCT. The habits each form teaches are sound for that form and expensive on the other. A JCT quantity surveyor who values an NEC compensation event at the bill rate has answered the wrong question. An NEC commercial manager who waits for a JCT architect to accept a programme will wait forever, because the contract never asks for it.
I have first-hand experience of this. I worked on an NEC3 Option B contract that the Project Manager administered in the same manner as a JCT contract: unwilling to entertain compensation events built up from Defined Cost, agreeing only to bill rates, and never accepting the clause 32 programme revisions. Administering an NEC contract this way does not help anyone.
This article sets out the differences that change outcomes on a live project, what stays the same, and what to do differently when you move between the two. I compare the JCT Standard Building Contract 2016 (SBC/Q 2016, with quantities) with the NEC4 Engineering and Construction Contract, and note where the JCT Design and Build Contract and NEC3 differ. I give JCT clause numbers for SBC/Q 2016 and paraphrase both contracts throughout. Your contract will have amendments, so treat this as orientation and read your own.
The short version
| JCT SBC/Q 2016 | NEC4 ECC | |
|---|---|---|
| How change is handled | Three routes: variations, extensions of time, loss and expense | One route: the compensation event covers time and money together |
| Basis of valuing change | Contract rates and prices first, then pro-rata, fair rates or dayworks (Valuation Rules, 5.6) | Forecast effect on Defined Cost plus the Fee; rates only if both parties agree |
| When change is valued | Often after the work, through the final account | Before or during the work, on a forecast that is then final |
| Delay | Contractor's notice of delay, Architect fixes a later Completion Date (2.27, 2.28) | Movement in planned Completion on the Accepted Programme (63.5; 63.3 in NEC3) |
| The programme | A master programme, not a contract document, not accepted | The Accepted Programme, with a set content, accepted or rejected for stated reasons |
| Deadlines | Notices required, but late notice does not of itself end entitlement | Eight-week time bar on the Contractor; treated acceptance against the Project Manager |
| Weather | Exceptionally adverse weather gives time, not money (2.29.9) | One-in-ten-year test against stated data gives time and money, for the excess only |
| Ground risk | Generally with the Contractor | Unforeseeable physical conditions are a compensation event (60.1(12)) |
| Who administers | Architect or Contract Administrator, with a Quantity Surveyor valuing | Project Manager; the Supervisor deals with quality and Defects |
| Managing risk | Largely reactive; collaborative working as a supplemental provision | Early warning, Early Warning Register and regular early warning meetings |
The rest of this article explains each row and what it changes.
The vocabulary
The two contracts often describe the same thing with different words, and the wrong word in a letter tells the other side which contract you are really thinking in.
| JCT | NEC4 | Note |
|---|---|---|
| Employer | Client | NEC3 also says Employer |
| Architect / Contract Administrator | Project Manager | The NEC role is more active and runs the change process |
| Quantity Surveyor | No equivalent role | The Project Manager assesses; the Client's QS works under delegated authority |
| Clerk of works | Supervisor | The Supervisor's role is defined in the contract |
| Contract Sum | the Prices | |
| Contract Bills, Drawings and Specification | Scope (Works Information in NEC3) | |
| Variation | A compensation event (a change to the Scope is only one of them) | |
| Relevant Event / Relevant Matter | A compensation event | One list does both jobs |
| Practical Completion | Completion | Defined by what the Scope says must be done |
| Rectification Period | defects date and defect correction period | NEC sets a specific time for each Defect |
| Liquidated damages | delay damages (Option X7) | NEC needs no non-completion certificate |
| Provisional sums | None | NEC does not use them |
Difference 1: one mechanism for time and money
Under JCT, change runs down three separate tracks. A Variation is valued under the Valuation Rules in section 5. Delay is dealt with by the Contractor's notice of delay and the Architect's decision on a later Completion Date, by reference to a list of Relevant Events (2.27 to 2.29). The money for delay and disruption is recovered as loss and expense, by reference to a separate list of Relevant Matters (4.20 to 4.24).
The lists overlap without matching. Exceptionally adverse weather is a Relevant Event and gives time, but it is not a Relevant Matter and gives no money. The tracks have different procedures and different timetables. The Architect has twelve weeks from a notice to decide an extension and can review all extensions up to twelve weeks after Practical Completion. Loss and expense is ascertained on applications that come in as the job goes. It is common for a contractor to get time without money, or to agree the measured variation account long before anyone has looked at the prolongation.
NEC has one track. A compensation event carries its time and its cost together: one notification, one quotation covering the change to the Prices and the delay to the Completion Date and any Key Date, and one assessment. The events in clause 60.1, twenty-one of them in NEC4 plus any added by the Options and the Contract Data, are the single list for both. If something is a compensation event, it carries whatever time and cost it causes.
What this changes. You cannot park the time argument and chase the money later, or the reverse. The quotation deals with both, and the programme is part of the price submission. For an assessor, a quotation with a cost build-up and no programme analysis is incomplete wherever delay is claimed. For a contractor, the prolongation cost that a JCT contractor would gather into a loss and expense claim near the end has to be identified event by event, as it arises. That is harder work, and it produces a clearer answer much sooner.
Difference 2: cost, not tender rates
Under SBC/Q 2016 a Variation is valued by the Quantity Surveyor under the Valuation Rules. Where the work is of similar character and done under similar conditions, the bill rates apply. Where the conditions differ, the bill rates are the basis with a fair allowance for the difference. Where there is nothing comparable, a fair valuation is made, and dayworks are the fallback where the work cannot properly be measured. The tender is, in effect, the price list for change, even if a rate in it was priced wrongly. The contract also offers an alternative: the Architect can ask for a Schedule 2 Variation Quotation, so that the price and any extension of time are agreed before the work is done.
Under NEC the starting point is cost. A compensation event is assessed as its effect on Defined Cost, built up from the Schedule of Cost Components for the main Option, plus the Fee. That applies even under the priced Options A and B, where you might expect the activity schedule or the bill to govern. Rates and lump sums are used instead only if the Project Manager and the Contractor agree (clause 63.2 in NEC4).
An invented illustration. A contractor's bill rate for a class of concrete is £145 per cubic metre, priced keenly at tender, and its real cost of placing that concrete on this site is about £170. An instruction adds 200 cubic metres. Under the JCT Valuation Rules the additional concrete is valued at or near the £145 bill rate, and the contractor loses about £25 on every extra cubic metre, roughly £5,000 on this instruction before overheads. Under NEC the additional concrete is assessed at its forecast Defined Cost plus the Fee. The tender pricing of the original work is untouched, and the change is neither a penalty nor a windfall. Reverse the figures and the point holds the other way: a contractor with a generous bill rate does not get to apply it to the change.
What this changes. A contractor cannot rely on a well-priced bill item to make a margin on change, and an assessor cannot hold a contractor to a badly priced one. Both need to know the Schedule of Cost Components for their Option and edition, because it decides which costs count. The evidence changes too. A rate is proved by pointing at the bill. Defined Cost is proved with records for the past and a reasoned build-up for the future: people, Equipment, Plant and Materials, subcontractors, with quantities, outputs and durations that can be checked. And the Fee percentage, which many tenderers treat as an afterthought, turns out to be the contractor's entire recovery of overheads and profit on change.
The nearest JCT comes to the NEC approach is the Schedule 2 quotation, and it is worth noticing that JCT teams who use it well tend to adapt to NEC quickly. They are already used to pricing change in advance and agreeing time with it.
Difference 3: a forecast now, not an account later
This is the largest difference, and the one that takes longest to absorb.
JCT change is mostly settled by looking back. Variations are often measured and valued after the work is done. Loss and expense is, by its nature, a claim for loss and expense actually incurred. Extensions of time can be reviewed after Practical Completion. The culture that results is familiar to anyone who has worked on the form: keep records, keep building, and sort it out in the final account.
NEC is designed to settle each event when it happens, on a forecast. Under clause 63.1, work done before the dividing date is assessed at actual Defined Cost and everything after it is forecast. Once the event is implemented, the assessment is not revised because the forecast turns out to have been wrong. The only routes back in are the dispute procedure or the correction of an assumption the Project Manager stated when instructing the quotation.
What this changes. The quotation is the Contractor's one opportunity. If the forecast is light, the Contractor carries the shortfall. If it is generous and accepted, the Client cannot recover the difference when actual cost comes in lower. That is why the contract includes risk allowances inside the assessment: the Contractor is being asked to price risk and is paid for carrying it. A JCT quantity surveyor's instinct is to strip contingency out of a valuation. Under NEC, a reasoned risk allowance for a named risk belongs in the assessment. I cover how to build and test one in the article on risk allowances.
It also changes what the final account is. If the contract is run as written, the NEC final account is arithmetic: the tendered Prices plus the implemented compensation events. There is nothing left to negotiate at the end, because every event was closed during the job. Few projects achieve that fully, but the closer a project gets, the less there is to fight about.
In practice the parties often fail to run it that way. Quotations run late, assessments run later, and by the time anyone looks at an event the work is finished and there is pressure to drop the forecast and use actual cost. My view is that the contract is clear about the date at which the assessment switches from actual to forecast, and that date does not move because the parties were slow.
Difference 4: the programme is the measuring stick
Under SBC/Q 2016 the Contractor provides a master programme, but it is not a contract document, the Architect does not accept it, and the contract does not use it to fix an extension of time. The Contractor gives notice of delay when it becomes reasonably apparent, with the expected effects and an estimate of the delay. The Architect then fixes a later Completion Date if a Relevant Event is likely to delay completion beyond the current date, within twelve weeks of the notice where that is possible. How the delay is analysed is left open, and on a disputed project it becomes a contest between experts.
NEC names the method. Clause 63.5 of NEC4 (63.3 in NEC3) measures delay as the movement in planned Completion against the Accepted Programme current at the dividing date. The Accepted Programme is a contract document with a set list of content: planned Completion, the order and timing of operations, float, time risk allowances, the dates the Contractor needs things from the Client, and a statement of how each operation will be done. The Contractor revises it at the interval in the Contract Data, and the Project Manager accepts it or rejects it within two weeks for one of four reasons the contract lists. Under NEC4, a Project Manager who stays silent after a reminder is treated as having accepted it.
What this changes. Keeping the Accepted Programme current is a commercial job as well as a planning one. If the Contractor has not submitted a programme the contract requires, or the Project Manager has not accepted the latest one for a reason the contract allows, the Project Manager can assess the compensation event itself (clause 64.1). A contractor in that position has lost control of the time half of every event. I explain how that assessment is meant to work in the Project Manager's own assessment.
Float is settled more clearly too. Float before planned Completion is available to absorb a compensation event. The terminal float between planned Completion and the Completion Date stays with the Contractor, because delay is measured by the movement of planned Completion. Under JCT the question of who owns float is left to the facts and the experts.
Difference 5: deadlines on both sides, with consequences
JCT asks for notices, and SBC/Q 2016 asks for loss and expense applications as soon as the likely effect becomes reasonably apparent, with supporting information. But a late notice does not, of itself, end the Contractor's entitlement. The Architect can still take the event into account, and the loss and expense clause is expressly without prejudice to the Contractor's other remedies.
NEC sits at the strict end and applies the discipline to both parties. For events the Contractor has to notify, clause 61.3 removes the right to a change in the Prices, the Completion Date or a Key Date if notification comes more than eight weeks after the Contractor became aware that the event happened. There is an exception for events arising from the Project Manager's or Supervisor's own instructions, notifications, certificates and changed decisions, and the wording of that exception differs between NEC3, the April 2013 NEC3 reprint and NEC4. On the other side, the Project Manager has one week to reply to a notification and two weeks to reply to a quotation. If the Project Manager stays silent after a reminder, the contract treats the silence as acceptance, including acceptance of the quotation as submitted (clauses 61.4, 62.6 and 64.4).
What this changes. Both teams need a register that tracks dates as well as values. For the Contractor, the critical date is awareness of the event, which usually comes on site well before anything reaches the commercial team. For the Project Manager it is every reply period currently running. I have written separately about the eight-week time bar and deemed acceptance, because those two mechanisms cause more avoidable loss than anything else in the contract. The free timeline calculator works out the dates for NEC3 and NEC4.
Difference 6: weather and ground
Two risks show the difference in drafting style better than anything else.
Weather. Under SBC/Q 2016, exceptionally adverse weather is a Relevant Event (2.29.9; 2.26.8 in DB 2016). It gives time and no money, and the contract does not say what "exceptionally adverse" means. Whether it applies depends on the time of year and the location, and in practice the argument is usually settled by asking how often weather like it occurs, often with a once-in-ten-years frequency in mind.
NEC writes that test into the contract and makes it measurable. Clause 60.1(13) compares the weather recorded in a calendar month, at a place stated in the Contract Data, against historical weather data, and the event happens only if the measurement would occur on average less than once in ten years. It gives money as well as time, but only for the difference between the recorded weather and the one-in-ten-year weather, not for the whole wet month. JCT habits on both sides go wrong here: contractors claim the whole month, and Client teams argue about whether the weather was "exceptional", which is not the NEC question.
Ground. JCT building contracts generally leave ground risk with the Contractor unless the parties amend them. NEC makes physical conditions within the Site a compensation event if an experienced contractor would, at the Contract Date, have judged them to have such a small chance of occurring that it would have been unreasonable to allow for them (60.1(12)). Only the difference between what was found and what it would have been reasonable to allow for counts. For a contractor moving from JCT to NEC this is real protection, provided the Site Information has been read and the tender allowed for what it shows.
Difference 7: who administers, and how early
Under JCT the Architect or Contract Administrator issues instructions, decides extensions of time and certifies, and the Quantity Surveyor values variations and ascertains loss and expense. Much of the traditional final account is a negotiation between two quantity surveyors.
NEC concentrates the administration in the Project Manager, who acts for the Client, instructs change, accepts programmes and assesses compensation events. The Supervisor deals with tests, inspections and Defects. There is no quantity surveyor in the contract at all. The Client's commercial team works through the Project Manager's delegated authority, and the delegation needs to be written down, because a reply from someone without authority may not be a reply.
NEC also gives both parties a tool JCT lacks in its main conditions: early warning. Either party must notify anything that could increase the Prices, delay Completion or a Key Date, or impair the performance of the works. The matter goes on the Early Warning Register and is discussed at an early warning meeting, where the aim is to avoid or reduce its effect. Under NEC4 the Project Manager issues the first register within a week of the starting date and holds the first meeting within two weeks. The sanction sits in the compensation event: where an experienced contractor could have given an early warning and this one did not, the event is assessed as if the warning had been given.
JCT 2016 does include a collaborative working provision among its supplemental provisions, but it is a statement of how the parties should behave rather than a process with dates and consequences.
What this changes. Problems are meant to be raised while something can still be done about them. A JCT contractor who keeps quiet about a looming problem to protect a later claim is acting against its own interest under NEC.
The same change, run both ways
An invented example shows how the differences add up. In month five of a twelve-month project, the designer revises the foundations in one area after a ground investigation result. The revision adds work and holds up the frame in that area for three weeks.
Under JCT SBC/Q 2016. The Architect issues an instruction with the revised drawings. The Contractor gives notice of delay and carries on. The quantity surveyors measure the revised foundations and value them at bill rates over the next two or three valuations, with some argument about whether the deeper excavation is work of similar character done under similar conditions. The Architect fixes a later Completion Date, granting two of the three weeks within the twelve-week period and reserving the review after Practical Completion. The prolongation costs go in as a loss and expense application, which is finally ascertained as part of the final account a year or more after the event. Each party carries uncertainty about time and money for most of the project.
Under NEC4. The Project Manager instructs the change, notifies the compensation event and instructs a quotation in the same communication. That fixes the dividing date. Within three weeks the Contractor submits a quotation: the forecast Defined Cost of the revised foundations less that of the original design, a stated risk allowance for the ground, the Fee, and an impacted programme showing that two weeks of float are absorbed and planned Completion moves by one week, with the time-related cost of that week included. The Project Manager replies within two weeks, queries one output, and accepts a revised quotation three weeks later. About eight weeks after the instruction, the Prices and the Completion Date have changed, and neither can be reopened because the ground turns out better or worse than forecast.
The NEC route demanded more from both teams in those eight weeks than the JCT route did in the same period. In return, both parties had certainty ten months earlier. That is the bargain NEC offers, and it only pays off if both sides do the work inside the periods. If they do not, they get NEC's administration and a JCT-style final account as well.
What stays the same
The differences are real, and the fundamentals still carry over.
- Entitlement is decided by the words of the contract, and the contract is the amended version the parties signed.
- Causation has to be shown. The event has to be the reason for the cost and the delay.
- Records decide most arguments, and records made at the time beat reconstruction.
- The party asking for money has to prove the amount.
- The quality of the file decides the outcome more often than the merits do.
If anything, NEC raises the standard. A JCT final account allows months to assemble the evidence; an NEC quotation allows three weeks. My guide to substantiating a compensation event sets out what an assessor needs to see in that time.
Which is better?
Neither, in the abstract. They allocate risk and administration differently, and each suits some projects and some teams better.
JCT's case is familiarity and certainty of meaning. The building sector is set up around it, its wording has been tested in the courts for decades, and a well-run JCT job with a capable Contract Administrator works perfectly well. Its weaknesses show on projects with a lot of change: three separate tracks for time and money, no binding programme, no time bar on late claims, and a final account that can be argued over long after the people who knew the facts have moved on.
NEC's case is that it is a management tool rather than a document for the drawer. It forces change to be priced and agreed as it happens, it gives both parties firm deadlines, it uses objective tests where JCT uses judgement, and it lets risk be allocated project by project. Its weakness is that it demands resource. A Project Manager who administers it like a JCT Contract Administrator, or a contractor without the commercial and planning capacity to meet the periods, gets the burden without the benefit.
For subcontractors there is a practical point. Your subcontract will usually follow the main contract form, and NEC subcontracts carry the same time bar and the same quotation periods, often shortened by amendment. A subcontractor used to JCT subcontracts who signs an NEC subcontract without changing how it notifies and quotes is the business most exposed to the differences in this article.
Moving from JCT to NEC
If you are a contractor's quantity surveyor, stop thinking in rates and start thinking in resources. Learn the Schedule of Cost Components for your main Option and edition. Set up site records so that cost can be allocated to events from the first day. Treat the three-week quotation period as the deadline it is, and ask for an extension before it expires if you need one.
If you are a Project Manager or on the Client's commercial team, run the reply periods as a daily discipline. Notify and instruct quotations with your own instructions, so the process starts on a known date. Assess against clause 63, which means Defined Cost, the programme and risk allowances, not a general sense of fairness. Accept or reject programmes properly and on time.
If you are a planner, you now hold half of every compensation event. A programme that is submitted on time, shows real logic and is accepted is worth more to the business than any claim document.
If you are a director, the question to ask about an NEC project is how many compensation events are open, how old they are and whose clock is running. A large number of old events is the NEC version of an unagreed JCT final account, and the contract gives both parties the tools to prevent it.
Frequently asked questions
What is the main difference between JCT and NEC? How change is handled. JCT values variations from contract rates and deals with time and loss and expense separately, often after the event. NEC deals with each compensation event once, before or during the work, on forecast cost plus the Fee, with time and money together, inside fixed periods.
Is a compensation event the NEC version of a variation? Partly. A change to the Scope is one compensation event among twenty-one in NEC4. The same mechanism also covers Client failures, physical conditions, weather, prevention and other Client risks, so it does the work of JCT's Variations, Relevant Events and Relevant Matters together.
Is there loss and expense under NEC? Not as a separate claim. Delay and disruption costs are part of the compensation event's effect on Defined Cost and go in the same quotation.
Is there an extension of time under NEC? Not by that name. A compensation event that delays planned Completion changes the Completion Date, assessed in the same quotation as the cost.
Does NEC have a time bar and JCT not? Under the standard forms, yes. NEC's clause 61.3 removes the right to a change in the Prices and dates for events the Contractor notifies more than eight weeks after becoming aware of them, with an exception for events arising from the Project Manager's or Supervisor's own actions. JCT requires notices, but a late notice does not of itself end the entitlement. Amendments to either form can change this.
Which contract do public sector clients use? Both are used. NEC is widely used on public sector infrastructure and many frameworks offer both forms, while JCT remains the most common form on building work. The choice is usually made project by project.
Where Clause 60 fits
The common thread in every difference above is that NEC asks for more analysis, earlier, inside fixed periods, from people who are already busy, and that it punishes JCT habits. Clause 60 is built for that. It reads a compensation event pack, including the quotation and cost build-up, the contract with its Z-clauses, and the native programme from Primavera P6 or Microsoft Project, and returns a structured first-pass review in about ten minutes. Sections are RAG-rated, findings are cited to their source documents and labelled Fact or Inference, and gaps are flagged. It is assistive, not advisory: the professional checks it and signs it off.
There is a full review of a sample NEC4 event, with the complete report, at clause60.com/demo. No sign-up is needed.
This article is general guidance written from professional experience. It describes standard forms in summary and is not legal advice. It does not account for the amendments in your contract. NEC is a registered trade mark of its owner and JCT is the mark of its owner; Clause 60 Limited is not affiliated with or endorsed by either.